Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

16.11 Closure of southern road (direction Warszawa) on section 220km+900-224km+900, two way passage on northern roadway (direction Świecko). Emergency entrance on 221km+443 is closed for passage for the time of works.
23-26.11 Section 216km+900-220km+900 of southern road (direction Warszawa) reintroduced for passage.
27.11-6.12 works on trunk road DW466 within A2 motorway, near Słupca Interchange. Alternate closure of western and eastern roadway, two way passage conducted with traffic lights or manually to provide the fluency of passage. Closure of slip road A with a passage from Słupca I/C from DW466 to Warszawa - passage lead through Słupca, left on the crossroad to DK92 till Września and then according to road signs to A2 Warszawa.
27-30.11 Closure of southern road (direction Warszawa) on section 224km+900-228km+300, two way passage on northern roadway (direction Świecko).
1-3.12 Section 220km+900-224km+900 of southern road (direction Warszawa) reintroduced for passage.

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 16.11 Closure of southern road (direction Warszawa) on section 220km+900-224km+900, two way passage on northern roadway (direction Świecko). Emergency entrance on 221km+443 is closed for passage for the time of works.
  • 18.11-15.12 works on trunk road DW466 within A2 motorway, near Słupca Interchange. Alternate closure of western and eastern roadway, two way passage conducted  with traffic lights or manually to provide the fluency of passage.
  • 23-26.11 Section 216km+900-220km+900 of southern road (direction Warszawa) reintroduced for passage.
  • 23-26.11 Closure of southern road (direction Warszawa) on section 224km+900-228km+300, two way passage on northern roadway (direction Świecko).
  • 1-3.12 Section 220km+900-224km+900 of southern road (direction Warszawa) reintroduced for passage.
  • 1-3.12 Closure of southern road (direction Warszawa) on section 228km+300-232km+300, two way passage on northern roadway (direction Świecko).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 13-19.11 works on trunk road DW467 within A2 motorway, near Sługocin Interchange. Closure of roadway DW467 over the motorway - alternate western and eastern roadway, two way passage conducted with traffic lights or manually to provide the fluency of passage.
  • 16.11 Closure of southern road (direction Warszawa) on section 220km+900-224km+900, two way passage on northern roadway (direction Świecko). Emergency entrance on 221km+443 is closed for passage for the time of works.
  • 17-19.11 Section 216km+900-220km+900 of southern road (direction Warszawa) reintroduced for passage.
  • 17-19.11 Closure of southern road (direction Warszawa) on section 224km+900-228km+300, two way passage on northern roadway (direction Świecko).
  • 18.11-15.12 works on trunk road DW466 within A2 motorway, near Słupca Interchange. Alternate closure of western and eastern roadway, two way passage conducted with traffic lights or manually to provide the fluency of passage.
  • 24/25.11 Section 220km+900-225km+900 of southern road (direction Warszawa) reintroduced for passage.
  • 26/27.11 Closure of southern road (direction Warszawa) on section 228km+300-232km+300, two way passage on northern roadway (direction Świecko).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00 a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 4/.11 Closure of southern road (direction Warszawa) on section 212km+950-216km+950, two way passage on northern roadway (direction Świecko). Emergency entrance on 216km+438 is closed for passage for the time of works – one-day closure of CSA Gozdowo.
  • 9.11 Section 209km+450-212km+950 of southern road (direction Warszawa) reintroduced for passage.
  • 9-11.11 Closure of southern road (direction Warszawa) on section 216km+950-220km+900, two way passage on northern roadway (direction Świecko).
  • 15/16.11 Section 212km+950-216km+950 of southern road (direction Warszawa) reintroduced for passage.
  • 15/16.11 Closure of southern road (direction Warszawa) on section 220km+900-224km+900, two way passage on northern roadway (direction Świecko). Emergency entrance on 221km+443 is closed for passage for the time of works.
  • 20/21.11 Section 216km+900-220km+900 of southern road (direction Warszawa) reintroduced for passage.
  • 20/21.11 Closure of southern road (direction Warszawa) on section 224km+900-228km+300, two way passage on northern roadway (direction Świecko).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 2/3.11 Closure of southern road (direction Warszawa) on section 209km+450-212km+950, two way passage on northern roadway (direction Świecko).
  • 4/5.11 Closure of southern road (direction Warszawa) on section 212km+950-216km+950, two way passage on northern roadway (direction Świecko). Emergency entrance on 216km+438 is closed for passage for the time of works – one-day closure of CSA Gozdowo.
  • 8/9.11 Section 209km+450-212km+950 of southern road (direction Warszawa) reintroduced for passage.
  • 8/9.11 Closure of southern road (direction Warszawa) on section 216km+950-220km+900, two way passage on northern roadway (direction Świecko).
  • 11/12.11 Section 212km+950-216km+950 of southern road (direction Warszawa) reintroduced for passage.
  • 11/12.11 Closure of southern road (direction Warszawa) on section 220km+900-224km+900, two way passage on northern roadway (direction Świecko). Emergency entrance on 221km+443 is closed for passage for the time of works.

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 25/26.10 Section 212km+950-216km+950 of northern road (direction Świecko) reintroduced for passage.
  • 28/29.10 Section 209km+450-212km+950 of northern road (direction Świecko) reintroduced for passage.
  • 2/3.11 Closure of northern road (direction Świecko) on section 209km+450-212km+950, two way passage on southern roadway (direction Warszawa).
  • 4/5.11 Closure of northern road (direction Świecko) on section 212km+950-216km+950, two way passage on southern roadway (direction Warszawa). Emergency entrance on 216km+438 is closed for passage for the time of works – one-day closure of CSA Gozdowo.
  • 8/9.11 Section 209km+450-212km+950 of northern road (direction Świecko) reintroduced for passage.
  • 8/9.11 Closure of northern road (direction Świecko) on section 216km+950-220km+900, two way passage on southern roadway (direction Warszawa).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

PAVEMENT RENOVATION OF A2 ON SECTION WRZEŚNIA-KONIN

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway.

Schedule of works:

  • 12.10 Closure of northern road (direction Świecko) on section 216km+950-220km+900, two way passage on southern roadway (direction Warszawa).
  • 14/15.10 Section 220km+900-224km+900 of norhern road (direction Świecko) reintroduced for passage.
  • 14/15.10 Closure of northern road (direction Świecko) on section 212km+950-216km+950, two way passage on southern roadway (direction Warszawa).
  • 17.10-18.10 Closure of emergency entrance on 216km+490 for the time of works, one-day closure of exit road to Sołeczno CSA from 7.00 to 7.00 p.m.
  • 19/20.10 Section 216km+950-200km+900 of norhern road (direction Świecko) reintroduced for passage.
  • 19/20.10 Closure of northern road (direction Świecko) on section 209km+450-212km+950, two way passage on southern roadway (direction Warszawa).
  • 23/24.10 Section 212km+950-216km+950 of norhern road (direction Świecko) reintroduced for passage.
  • 26/27.10 Section 209km+450-212km+950 of norhern road (direction Świecko) reintroduced for passage.

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be
temporal traffic system on pointed sections of motorway. Schedule of works:

  • 2.10 Closure of northern road (direction Świecko) on section 220km+900-224km+900, two way passage on southern roadway (direction Warszawa). Emergency entrance on 221km+628 is closed for passage for the time of works.
  • 12.10 Closure of northern road (direction Świecko) on section 216km+950-220km+900, two way passage on southern roadway (direction Warszawa).
  • 14/15.10 Section 220km+900-224km+900 of norhern road (direction Świecko) reintroduced for passage.
  • 14/15.10 Closure of northern road (direction Świecko) on section 212km+950-216km+950, two way passage on southern roadway (direction Warszawa). Emergency entrance on 216km+490 is closed for passage for the time of works, one-day closure of exit road to Sołeczno CSA.
  • 19/20.10 Section 216km+950-200km+900 of norhern road (direction Świecko) reintroduced for passage.
  • 19/20.10 Closure of northern road (direction Świecko) on section 209km+450-212km+950, two way passage on southern roadway (direction Warszawa).
  • 23/24.10 Section 212km+950-216km+950 of norhern road (direction Świecko) reintroduced for passage.

Schedules presented above can change, due to weather conditions and current traffic intensity within
section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public
motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of
the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate
for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp
and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 22.09 Closure of northern road (direction Świecko) on section 228km-229, two-way passage on southern roadway (direction Warszawa). Closure of CSA Skarboszewo (226km+500) and service gate on CSA.
  • 22.09 Closure of northern road (direction Świecko) on section 224km+900-232km+300, two-way passage on southern roadway (direction Warszawa). Emergency entrance on 229km+173 is closed for passage for the time of works.
  • 26.09 Słupca Interchange: closure of slip road D with a passage from A2 in direction of Świecko to DW466 in direction of Słupca. Passage to Słupca and Pyzdry lead by detour:
    • Direction Słupca - A2 to Września I/C, then DK92 through Września till Słupca
    • Direction Pyzdry - A2 to Września I/C, then from DK92 to DW442 till Pyzdry
  • 2/3.10 Closure of northern road (direction Świecko) on section 220km+900-224km+900, two way passage on southern roadway (direction Warszawa). Emergency entrance on 221km+628 is closed for passage for the time of works.
  •  5/6.09 Section 224km+900-223km+300 of northern road (direction Świecko) reintroduced for passage.
  • 5/6.10 Closure of northern road (direction Świecko) on section 216km+950-220km+900, two way passage on southern roadway (direction Warszawa).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 11/12.09 Closure of northern road (direction Świecko) on section 236km+200-240km+100, two-way passage on southern roadway (direction Warszawa). Emergency entrance on 237km+917 is closed for passage for the time of works.
  • 17/18.09 Closure of northern road (direction Świecko) on section 232km+300-236km+200, two-way passage on southern roadway (direction Warszawa).
  • 17/18.09 closure of bridge object MA68 and section 245km+600-246km+100 of southern road (direction Warszawa) for 7 working days, two-way passage on northern roadway (direction Świecko)
  • 20/21.09 Section 238km+900-240km+100 of northern road (direction Świecko) reintroduced for passage.
  • 22/23.09 Section 236km+200-238km+200 of northern road (direction Świecko) reintroduced for passage.
  • 22/23.09 Closure of northern road (direction Świecko) on section 224km+900-232km+300, two-way passage on southern roadway (direction Warszawa). Closure of CSA Skarboszewo (226km) and service gate on CSA.
  • 24/25.09 Section 232km+300-236km+200 of northern road (direction Świecko) reintroduced for passage.
  • 24/25.09 Closure of northern road (direction Świecko) on section 220km+900-224km+900, two-way passage on southern roadway (direction Warszawa). Estimated time of works is 5-7 days. Emergency entrance on 221km+628 is closed for passage for the time of works.
  • 25/26.09 Słupca Interchange: closure of slip road D with a passage from A2 in direction of Świecko to DW466 in direction of Słupca. Passage to Słupca and Pyzdry lead by detour:
    • Direction Słupca - A2 to Września I/C, then DK92 through Września till Słupca
    • Direction Pyzdry - A2 to Września I/C, then from DK92 to DW442 till Pyzdry

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Renovation works on trunk road DK2, DK29 and slip roads on Świecko Interchange

On Friday, 1st of September begun another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29, DK2 and slip roads C, C1, D, D1, E of Świecko Interchange. The renovation of mentioned objects will last till 8th of September.

Scheduled working schemes:

  • 1.09-8.09 Continuation of works on DK29 and slip roads C, C1, D, D1, E - works connected to reconstruction of horizontal marking, roadside cambering, regulation of gutters and resilient bars on slip roads.
  • 1.09-8.09 works on left roadway of DK2 (direction Świecko) - renovation of left and half of right lane, section 2+800km - 3+375km

Schemes of works can be changed depending on the weather conditions and current traffic intensity within the Interchange.

Works are conducted within Świecko Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 5.09 Closure of northern road (direction Świecko) on section 240km+100-244km+200, two-way passage on southern roadway (direction Warszawa).
  • 7/8.09 Closure of slip road A with a passage on Sługocin Interchange from DW467 to A2 in direction of Poznań
  • 9/10.09 Section 244km+200-248km+100 of northern road reintroduced for passage.
  • 9/10.09 Closure of northern road (direction Świecko) on section 236km+200-240km+100, two-way passage on southern roadway (direction Warszawa). Emergency entrance on 237km+917 is closed for passage for the time of works.
  • 12/13.09 Section 240km+100-244km+200of northern road reintroduced for passage.
  • 12/13.09 Closure of northern road (direction Świecko) on section 232km+300-236km+200, two-way passage on southern roadway (direction Warszawa).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

On 20 August - 1 September begins next stage of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 20/21.08 Closure of northern road (direction Świecko) on section 252km+000-257km+560, two-way passage on southern roadway (direction Warszawa).
  • 23/24.08 Closure of northern road (direction Świecko) on section 248km+100-252km+000, two-way passage on southern roadway (direction Warszawa), emergency entrance on 248km+080 and 251km+138 closed for passage for time of works.
  • 28/29.08 Section 252km+000-257km+560 of northern road reintroduced for passage.
  • 28/29.08 Closure of northern road (direction Świecko) on section 244km+200-248km+100, two-way passage on southern roadway (direction Warszawa), emergency entrance on 248km+080 closed for passage for time of works.
  • 31.08/1.09 Section 248km+100-252km+000 of northern road reintroduced for passage.
  • 31.08/1.09 Closure of northern road (direction Świecko) on section 240km+100-244km+200, two-way passage on southern roadway (direction Warszawa).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Renovation works on trunk road DK2, DK29 and slip roads on Świecko Interchange

On Thursday, 17th of August begun another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29, DK2 and slip roads C, C1, D, D1, E of Świecko Interchange. The renovation of mentioned objects will last till 28th of August.

Scheduled working schemes:

  • 17.08-27.08 Continuation of works on DK29 and slip roads C, C1, D, D1, E - works connected to reconstruction of horizontal marking, roadside cambering, regulation of gutters and resilient bars on slip roads.
  • 17.08-20.08 works on right roadway of DK2 (direction Warszawa) - renovation of emergency and half of right lane, section 2+900km - 3+375km — STAGE 1
  • 20.08-23.08 works on right roadway of DK2 (direction Warszawa) - renovation of left and half of right lane, section 2+900km - 3+375km — STAGE 2
  • 23.08-28.08 works on left roadway of DK2 (direction Świecko) - partial renovation of left lane, section 3+375km - 2+046km — STAGE 3

Schemes of works can be changed depending on the weather conditions and current traffic intensity within the Interchange.

Works are conducted within Świecko Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Renovation works on trunk road DK2, DK29 and slip roads on Świecko Interchange

On Monday, 31st of July begun another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29, DK2 and slip roads C, C1, D, D1 of Świecko Interchange. The renovation of mentioned objects will last till 11th of August.

Scheduled working schemes:

  • 31.07-11.08 Continuation of works on DK29 and slip roads C, C1, D, D1 - works connected to reconstruction of horizontal marking, roadside cambering, regulation of gutters and resilient bars on slip roads.
  • 31.07-2.08 works on right roadway of DK2 (direction Warszawa) - renovation of emergency and half of right lane, section 2+046km - 2+469km — STAGE 1
  • 3.08-5.08 works on right roadway of DK2 (direction Warszawa) - renovation of left and half of right lane, section 2+046km - 2+469km — STAGE 2
  • 6.08-8.08 works on right roadway of DK2 (direction Warszawa) - renovation of emergency and half of right lane, section 2+469km - 2+869km — STAGE 3
  • 9.08-10.08 works on right roadway of DK2 (direction Warszawa) - renovation of left and half of right lane, section 2+469km - 2+869km — STAGE 4

Schemes of works can be changed depending on the weather conditions and current traffic intensity within the Interchange. Between 11.08 and 16.08 there will be a stoppage of renovation works.

Works are conducted within Świecko Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of Sługocin Interchange

On 24/25th of July begin works within Sługocin Interchange (244km of motorway), section Września-Konin. There will be temporal traffic system. With the closure of works within A2 motorway, works will be organized on slip road C (passage from Poznań to Interchange) and slip road D (exit from the Interchange to Warszawa). The renovation will last till about 5-7 days. Schemes of works can change depending on the weather conditions and current traffic intensity within the Interchange.

  • Passage from DW467 in direction of Warszawa lead to Golina, then on trunk road DK92 to Słupca, from Słupca by DW466 to Słupca Interchange
  • Passage from Poznań to Ciążeń lead from A2 motorway to Słupca Interchange, then right on DW466 to Ciążeń
  • Passage from Poznań to Golina lead from A2 motorway to Słupca Interchange, then left on DW466 to Słupca and next on trunk road DK92 to Golina.

Works are conducted within Sługocin Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with General Directorate for National Roads and Motorways in Poznań, Autostrada Wielkopolska Inc, Autostrada Eksploatacja Inc and appropriate Police units.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

On 23/24th of July starts next stage of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway. Schedule of works:

  • 23/2.07 Closure of southern road (direction Warszawa) on section 248km+100-252km+000, two-way passage on northern roadway (direction Świecko), emergency exit on 248km+078 closed for passage for time of works.
  • 26/27.07 Section 240km+100-244km+200 reintroduced for passage.
  • 26/27.07 Closure of southern road (direction Warszawa) on section 244km+200-248km+100, two-way passage on northern roadway (direction Świecko), emergency exit on 251km+000 closed for passage for time of works.
  • 29/30.07 Section 244km+200-248km+100 reintroduced for passage.
  • 29/30.07 Closure of southern road (direction Warszawa) on section 252km+000-255km+800, two-way passage on northern roadway (direction Świecko).
  • 31.07/1.08 Section 248km+100-252km+000 reintroduced for passage.
  • 31.07/1.08 Closure of southern road (direction Warszawa) on section 255km+800-257km+560, two-way passage on northern roadway (direction Świecko), emergency exit on 257km+288 closed for passage for time of works.

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Renovation works on trunk road DK2, DK29 and slip roads on Świecko Interchange

On Tuesday, 11th of July begun another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29, DK2 and slip roads C, C1, D, D1 of Świecko Interchange. The renovation of mentioned objects will last till 3rd of August.

Schemes of works (especially stages 3, 4, 5) can be changed depending on the weather conditions and current traffic intensity within the Interchange. There will be temporal traffic system.

Scheduled working schemes:

  • Continuation of works on DK29 and slip roads C, C1, D, D1 - works connected to reconstruction of horizontal marking, roadside cambering, regulation of gutters and resilient bars on slip roads. Scheduled finalization of works - 30.07.2017.
  • 11.07.2017 works on left roadway of DK2 (direction Świecko) - renovation of emergency and half of right lane, section 2,469km-2,869km; possible use of slip road D — scheme 1
  • 17.07—19/20.07.2017 works on left roadway of DK2 (direction Świecko) - renovation of left and half of right lane, section 2,469km-2,869km — scheme 2
  • 19/20.07—22/23.07.2017 works on left roadway of DK2 (direction Świecko) - renovation of left and half of right lane, section 2,046km-2,469km — scheme 3
  • 22/23.07—24/25.07.2017 works on left roadway of DK2 (direction Świecko) - renovation of emergency and half of right lane, section 2,046km-2,469km — scheme 4
  • 24/25.07—27/28.07.2017 works on final part of slip road C (on exit and part of DK2) - pavement layering — scheme 5
  • 31.07—2/3.08.2017 works on right roadway of DK2 (direction Warszawa) - renovation of emergency and half of right lane, section 2,046km-2,469km — scheme 6

 

Works are conducted within Świecko Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Pavement renovation of A2 on section Września-Konin

On Monday 10th of July at 6.00 starts pavement renovation of main road A2 motorway on section Września-Konin. First part of works is scheduled for the length from232km+300 to 236km+200 in direction of Warszawa. Southern roadway in direction of Warszawa will be closed for passage. There will be temporal traffic system. Passage in direction of Warszawa will be transferred to one lane of northern roadway (direction Świecko).

Sections of renovated road will be changed successively, depending on works progress.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using.

Works will last till October 2017.

 

The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Renovation works on trunk road DK29, DK2 and slip roads on Świecko Interchange

On Monday, 3rd of July begins another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29, DK2 and slip roads C, C1, D, D1 of Świecko Interchange. The renovation of mentioned objects will last till 17th of July.

Schemes of works will be changed depending on the weather conditions and current traffic intensity within the Interchange. There will be temporal traffic system.

Scheduled working schemes:

  • Continuation of works on DK29 - composition of binding layer and wearing course on road. Scheduled finalization of works - 5/6.07.2017.
  • 3.07—17.07.2017 works connected to reconstruction of horizontal marking, roadside cambering, regulation of gutters and resilient bars on slip roads C, C1, D, D1, on trunk road DK29  and renovated sections od DK2
  • 3/4.07—7/8.07.2017 works on left roadway of DK2 (direction Świecko) - renovation of left and half of right lane, section 2,869km-3,375km — scheme 1
  • 7/8.07—10/11.07.2017 works on left roadway of DK2 (direction Świecko) - renovation of right lane and emergency lane, section 2,869km-3,375km — scheme 2
  • 10/11.07—14/15.07.2017 works on left roadway of DK2 (direction Świecko) - renovation of left and half of right lane, section 2,469km-2,849km — scheme 3

Works are conducted within Świecko Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857). The finalization of this part of works is scheduled for the 17th of July. Dates and sequences can change.

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Renovation works on trunk road DK29 and slip roads on Świecko Interchange

On 18 of June begins another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29 and slip roads C, C1, D, D1 of Świecko Interchange. The pavement renovation of mentioned objects will last till 3rd of July.

Schemes of works will be changed depending on the progress of works. There will be temporal traffic system within the Interchange.

Scheduled working schemes:

  1. 19-21.06.2017 deep renovation of trunk road DK29
  2. 22-27.06.2017 composition of binding layer on trunk road DK29
  3. 28.06-3.07.2017 composition of wearing course on trunk road DK29

In the days between 19.06 and 7.03.2017 it is scheduled to conduct works connected to reconstruction of horizontal marking, roadside cambering, regulation of gutters and resilient bars on slip roads C, C1, D, D1.

Works are conducted within Świecko Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857). The finalization of this part of works is scheduled for the 3rd of July. Dates and sequences can change due to weather conditions and current traffic intensity.

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Renovation works on trunk road DK29 within Świecko Interchange

On 8/9 of June begins another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29. It’s second part out of three of renovation works planned to be executed on this Interchange. The pavement renovation of DK29 will last till 18th of June. Due to Corpus Christi period, between 14th and 18th of June all works will be stopped, to keep the drivability of Interchange.

Due to the complexity of works, schemes presented below will be changed depending on the progress of works. There will be temporal traffic system within the Interchange. Scheduled working schemes:

A) Milling of trunk road DK29 pavement

1. Renovation of western part of trunk road DK29 (section within slip road C and C1) with a passage from Słubice to Zielona Góra - passage reassigned to eastern road.

2. Renovation of western part of trunk road DK29 (section within slip road D and E) with a passage from Słubice to Zielona Góra - passage reassigned to eastern road.

3. Renovation of western part of trunk road DK29 (from A1 slip road in direction of Zielona Góra) with a passage from Słubice to Zielona Góra - passage reassigned to eastern road.

4. Renovation of eastern part of trunk road DK29 (from Zielona Góra to section at height A1 slip road) with a passage from Zielona Góra to Słubice - passage reassigned to western road.

5. Renovation of eastern part of trunk road DK29 (section at height within slip road D1 and A1) with a passage from Zielona Góra to Słubice - passage reassigned to western road. Projected time of works: 3 working days.

6. Renovation of eastern part of trunk road DK29 (section at height within slip road C and C1) with a passage from Zielona Góra to Słubice - passage reassigned to western road.

B) Layering of wearing course on trunk road DK29

7. Renovation of western part of trunk road DK29 (from Słubice to section at height of C1 slip road) with a passage from Słubice to Zielona Góra - passage reassigned to eastern road. Partial closure of slip road C - designated detour and traffic reassigned on slip road C1 with a passage from DK29 to Świecko.  

8. Renovation of western part of trunk road DK29 (section within slip road C1 and D) with a passage from Słubice to Zielona Góra - passage reassigned to eastern road. Closure of slip road C1 - designated detour and traffic reassigned on slip road C with a passage from DK29 to Świecko. 

9. Renovation of western part of trunk road DK29 (section within slip road D1 and A1) with a passage from Słubice to Zielona Góra - passage reassigned to eastern road. Partial closure of slip road D1 and D. Passage from Poznań to DK29 lead by detour and slip road C1. Passage from DK29 in direction of Poznań lead by detour and slip road A1. 

10. Renovation of western part of trunk road DK29 (section from slip road A1 in direction of Zielona Góra) - passage reassigned to eastern road. Closure of slip road A1 - passage from DK2 from Świecko to DK29 lead by detour and slip road E.

11. Renovation of eastern road of trunk road DK29 (section within slip road A and E) with a passage from Zielona Góra in direction of Słubice - passage reassigned to western road.

12. Renovation of eastern part of trunk road DK29 (section at height within slip road D1 and A1) with a passage from Zielona Góra to Słubice - passage reassigned to western road.

13. Renovation of eastern part of trunk road DK29 (section at height within slip road C and C1) with a passage from Zielona Góra to Słubice - passage reassigned to western road.

 

Works are conducted within Świecko Interchange. Renovation is mainly pavement construction milling and layering of wearing course. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857). The finalization of second part of works is scheduled for the 18th of June. Dates and sequences can change.

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)

Contact for media: Zofia Kwiatkowska, PR Manager, Spokesman, AWSA
tel. +48 608 479 541, email: z.kwiatkowska@mail.autostrada-a2.pl, http://www.autostrada-a2.pl/

Renovation works on and within Świecko Interchange

 

 

On the 15th of May, at 7.00 begins pavement renovation of slip roads on Świecko Interchange, on the crossroad of A2 motorway with trunk road DK29. All works will be conducted in three parts:

 

  1. Pavement renovation of slip roads on Świecko Interchange – scheduled for 15.05-8.06.2017
  2. Pavement renovation of trunk road DK29 – scheduled for 9.06-23.06.2017
  3. Pavement renovation of trunk road DK2 – scheduled for 24.06-15.08.2017

 

Dates are only approximate; schedule can warry due to weather conditions.

First part of Świecko Interchange renovation, the pavement of slip roads, will be divided into eight stages. None of relations on the Interchange will be closed, just narrowed. There will be temporal traffic system:

STAGE I: 15-17.05.2017 – Renovation of slip road B with a passage from trunk road DK29 from Zielona Góra to A2 in direction of Poznań and slip road E with a passage from trunk road DK29 from Słubice to A2 in direction of Poznań – milling and roads amendment, works on slip roads conducted separately.

STAGE II: 17-18.052017 – Renovation of slip road E with a passage from trunk road DK29 from Słubice to A2 in direction of Poznań – pavement layering.

STAGE III: 19-21.05.2017 – Renovation of slip road B with a passage from trunk road DK29 from Zielona Góra to A2 in direction of Poznań – pavement layering.

STAGE IV: 22-24.05.2017 – Renovation of slip road A with a passage from trunk road DK2 from Świeco to trunk road DK29 in direction of Słubice and Zielona Góra – milling, road amendment and pavement layering.

STAGE V: 25-26.05.2017 – Renovation of slip road C with a passage from trunk road DK29 Słubice and Zielona Góra to trunk road DK2 in direction of Świecko – milling and roads amendment, passage partially leaded on temporal road.

STAGE VI: 25-28.05.2017 – Renovation of slip road A with a passage from trunk road DK2 from Świeco to trunk road DK29 in direction of Słubice and Zielona Góra, slip road B with a passage from trunk road DK29 from Zielona Góra to A2 in direction of Poznań and slip road C with a passage from trunk road DK29 Słubice and Zielona Góra to trunk road DK2 in direction of Świecko (passage partially leaded on temporal road) – reconstruction of road surface markings, works on slip roads conducted separately.

STAGE VII: 29.05-1.06.2017 – Renovation of slip road C with a passage from trunk road DK29 Słubice and Zielona Góra to trunk road DK2 in direction of Świecko – pavement layering, passage partially leaded on temporal road.

STAGE VIII: 2.06.2017 – Renovation of slip road D with a passage from A2 from Poznań to trunk road DK29 in direction of Słubice and Zielona Góra – milling and roads amendment.

 

Works are conducted within and on Świecko Interchange, at the height of 2,0 to 3,4km of motorway. Renovation is mainly bracing the pavement that covers changes of wearing course and lower layers of construction (where’s needed). Renovation is guided on schedule, after 6 years from takeover by AWSAII into exploitation from General Directorate for National Roads and Motorways. Another modernization of Świecko Interchange area is planned for 2030.

Works are conducted in double day shift, renovation crop works also on alternate weekends.

The executor of the works is Strabag LLC. The finalization of works is scheduled for the 8th of June.

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.).

Osiecza MOP renovation works

On Monday, April 10th 2017, renovation works begin on Rest and Service Areas Osiecza II (251 km Świecko direction) and Osiecza III (251 km Warsaw direction). Portable toilet service will be available for the time of renovation. Completion of renovation works is scheduled for the end of June 2017.

We apologize for any inconveniences.

Modernization of ORLEN petrol stations

Continuation of ORLEN petrol stations modernization within A2 motorway. Works on CSA Osiecza II, Osiecza III and Sosna are finished. Schedule of next stages of works:

  • 134km, direction Warszawa, CSA Zalesie – works execution time: 23.01-6.03.2017.
  • 177km, direction Świecko, CSA Tulce – works execution time: 30.01-13.03.2017.

Scope of works: modernization of stations pavilion due to gastronomic offer extension within existing venues. Both buildings will be out of use and so will be the toilets. Petrol sales will be executed on two stands in temporary containers on both CSA’s.

Works on other objects (CSA Krzyżowniki and Sędzinko) are scheduled after the finalization of works on CSA Zalesie and Tulce.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00 a.m. and 8.00 p.m.)